FDOT US1 Mobility Improvement Project. Construction is anticipated to start in January 2023. Improvements planned include:
•
Milling and resurfacing along the project limits
• Modifying pavement markings along SR-5/US-1/Federal Highway to accommodate 4-foot bicycle lanes in each direction
• Installing 138 new light poles and upgrading existing lighting to LED along the corridor
• Replacing concrete sidewalk with pavers from Monroe Street to Van Buren Street, and from Polk Street to Fillmore Street
• Removing existing pavers at signalized intersections between Van Buren Street and SR-824/Pembroke Road
• Installing decorative stamped asphalt crosswalks at all signalized intersections
TRAFFIC IMPACTS
• Lane closures are permitted Sunday through Thursday, between 10:30 p.m. and 7:30 a.m. and two -hour single lane closures are permitted between 7:30am to 3:00pm for concrete pours.
• Full side street closures are permitted on weekends for the construction of the decorative crosswalks.
• Business, pedestrian, and residential access will be maintained at all times.
Construction Costs: $7,152,129 • Construction Start Date: January 2023 • Anticipated Completion: Early 2024
CONTACT INFORMATION
- Hugues Charles P.E. — FDOT Project Manager: hugues.charles@dot.state.fl.us or (954) 226-0255
- Alexander Vasquez — Project Administrator: avasquez@castilloeng.com or (305) 725-9767
- Rebecca Guerrero — Community Outreach Specialist: rguerrero@corradino.com or (954) 940-7605
- Jose Cortes — City of Hollywood: jcortes@hollywoodfl.org or (954) 240-7996