Construction began on October 17th along West Park Road between North Park Road and North 40th Avenue. This construction project includes swale restoration, milling and resurfacing of the existing road, new pavement markings, and sidewalk replacement within the project boundaries. The works is scheduled to take approximately 60 days to complete, pending weather or other unforeseen circumstances.
Access to private property will be maintained, however driveway access will be limited following a concrete pour to allow for the concrete to cure. In order to accommodate the inconvenience, temporary parking in the swale area adjacent to private property will be allowed while driveway access is temporarily closed. Closures are not expected to last longer than 48 hours.
For project questions or concerns please contact:
Raof Shams
CEI Project Manager
(954) 610-4482
raof.shams@tecgi.com
Navid Afshar
CEI Senior Inspector
(561) 289-7191
navid.afshar@tecgi.com
Mike Vlam
Contractor Project Manager
(954) 444-1059
mike@weekleyasp.com